Audit of the Massachusetts Department of Transportation - Millbury Roadway Reconstruction and Related Work (Contract 86774)
October 19, 2021 · Massachusetts Department of Transportation · Read the full official report on mass.gov ↗ · official site ↗
source
“Payments for police details were not always supported by MassDOT records.”
Read the plain-English breakdown
This is a State Auditor performance audit of a MassDOT roadway reconstruction and bridge replacement project in Millbury, covering work from September 3, 2015 through June 30, 2020.
“This report details the audit objectives, scope, methodology, findings, and recommendations for the audit period, September 3, 2015 through June 30, 2020.”
Auditors checked whether the project finished on time, whether extra work was approved properly, whether police detail payments were supported, and whether commodity price adjustments were handled correctly.
“In this performance audit, we determined whether MassDOT’s Project 605964, under Contract 86774, for roadway reconstruction (including bridge replacement) in Millbury was substantially completed1 in the budgeted timeframe, whether extra work orders were properly approved, whether payments for police details for traffic control were properly supported, and whether price adjustments for commodities were properly calculated and processed.”
If MassDOT records do not match the police invoices, the agency cannot be sure it paid the right amount for police traffic details.
“As a result, MassDOT cannot be certain it paid the correct amount in police detail costs related to this project.”
For ordinary residents, this audit is about whether public transportation money was tracked carefully on a local road and bridge project.
“Part of the project (85.7%) was financed by the Commonwealth, 11.8% by the federal government, and 2.5% by the town of Millbury.”
Most areas tested passed, but the audit found one police detail payment where invoices showed 24 more hours than MassDOT field reports, creating a possible $1,200 overpayment.
“The police invoices that corresponded to the CQE for this payment showed 24 more hours worked than the FIRs for the same dates, causing a possible overpayment of $1,200.”
The Auditor recommended that MassDOT require resident engineers to formally match police invoices against field inspection reports, and MassDOT said it was updating its procedures.
“MassDOT should develop and implement a formal policy requiring its resident engineer to reconcile all police department invoices for police details to the FIRs that correspond to each CQE.”
This was not a small paperwork review; it involved a major construction contract with an original bid price of more than $20 million.
“The original bid price of the contract was $20,444,070.”
A contract quantity estimate, or CQE, is the document MassDOT uses to record work completed and payments owed to the contractor.
“As construction takes place, MassDOT’s resident engineer maintains records of the amount of work completed at a given interval (usually two weeks) and prepares a document called a contract quantity estimate (CQE)3 at the end of each interval.”
What the Auditor checked
- Complied Did MassDOT send to the general contractor, within 65 days after the effective date of a declaration of substantial completion of Contract 86774, a substantial completion estimate documenting that the contract was substantially complete by the contract completion date?
- Complied Were extra work orders completed and approved in accordance with MassDOT’s Standard Operating Procedure SCD 25-12-1-000?
- Did not comply Did MassDOT have sufficient documentation, in accordance with its procedures, to support payments for police details for traffic control?
- Complied Did MassDOT properly calculate and process price adjustments for commodities used in performing Contract 86774, in accordance with Section 38A of Chapter 30 of the General Laws?
What the Auditor found
Why it matters: MassDOT cannot be certain it paid the correct amount in police detail costs related to the project.
Standard: Resident engineer review of police bills against official field inspection report hours before approving payment. ( Section 12 of Chapter 11 of the Massachusetts General Laws )
1 recommendation
- MassDOT should develop and implement a formal policy requiring its resident engineer to reconcile all police department invoices for police details to the FIRs that correspond to each CQE.agency: agreed
Agency response & Auditor reply
Agency: "MassDOT acknowledges the issue presented in the Report."
Auditor: "Based on its response, MassDOT is taking measures to address our concerns in this area."
Verified dollar findings
Estimated or sample-projected amounts - shown separately because they are not a hard-identified dollar figure.
More audits of this entity
Other Office of the State Auditor reports on Massachusetts Department of Transportation .
-
Close-out of Agencies and Authorities combined into the Massachusetts Department of TransportationState Agency / Office · October 18, 2012 -
Audit of Cybersecurity Awareness Training Compliance Across Multiple State Agencies - Massachusetts Department of TransportationState Agency / Office · November 8, 2024 -
Audit of the Massachusetts Department of Transportation Aeronautics DivisionState Agency / Office · June 30, 2022 -
The Department of Transportation's Office of Information Technology's Activities Relating to the Registry of Motor VehiclesState Agency / Office · July 20, 2011 -
Massachusetts Department of Transportation Use of Consultants and Contract EmployeesState Agency / Office · January 9, 2014 -
Massachusetts Department of Transportation Aeronautics DivisionState Agency / Office · August 18, 2017